26 MASH+ customers installed!

By end of today, Wednesday 17 September, Stephen Breheny and his 3 installation teams will have installed MASH+ solar systems for 23 customers.  That’s up from 18 systems at end of Friday 12 September. Steve says that there are 10 more pallets of solar panels left in his warehouse. Each pallet has 6Kw of solar power; so 60Kw more to install in this first bulk order – and that’s for 23 customers. Steve reckons that these remaining customers should be installed over the next 2-3 weeks and the next bulk order for 50 systems will be placed towards end of September.

Other progress on the MASH+ rollout is that Steve is expecting to have completed all the site visits by end of this week. He’s been working weekends to get around to everyone’s homes to make this happen. Good job, Steve!